Assigning work resources to tasks
The names of assigned resources
appear at the top of the list.
TIP To remove or unassign a resource from a selected task, in the Assign Resources
dialog box, click the resource name and then click Remove.
6
Next you’ll take a closer look at the details of task 3. You’ll use a handy view called
the Task Form.
8
On the View tab, in the Split View group, select the Details check box.
Project splits the window into two panes. In the upper pane is the Gantt Chart view,
and below it is the Task Form view.
The names of the view or views displayed appear here.
`