Customizing a Timeline view
3
Select the boxes for the following task names:
Planning Phase
Planning complete!
Internal Launch Phase
Public Launch Phase
Author travel and appearances
Use this dialog box to indicate tasks
you want to include in the Timeline view.
These tasks are summary tasks and a milestone task you will add to the Timeline
view.
4
Click OK .
Project adds the summary tasks and milestone to the Timeline view. If necessary,
adjust the horizontal divider bar between the Timeline and Gantt chart views so that
you can see more of the Timeline view.
Next you’ll adjust the formatting of the Author travel and appearances summary task
on the Timeline.
5
In the Timeline view, click the bar for the Author travel and appearances summary
task.