Microsoft Office Tutorials and References
In Depth Information
See task relationships with Task Path
Now you’ll more easily see the results of your next actions.
2
Click the name of task 29, Send to color house .
You’d like to identify this task’s predecessor and successor tasks.
3
On the Format tab, in Bar Styles group, click Task Path and then click Predecessors .
Project applies a gold highlight formatting to the Gantt bars of task 29’s predecessor
tasks.
As you can see in the view, task 29 has a chain of predecessor tasks. Next you’ll take a
closer look at the predecessor tasks that directly affect the scheduling of task 29.
9
4
On the Format tab, in the Bar Styles group, click Task Path and then click Driving
Predecessors .
Project applies a dark orange highlight formatting to the Gantt bars of this task’s
driving predecessor tasks.