Setting task constraints
Note the current scheduled start date: 7/15/15. This needs to be adjusted.
3
On the Task tab, in the Properties group, click Information .
4
In the Task Information dialog box, click the Advanced tab.
5
In the Constraint Type box, select Start No Earlier Than .
6
In the Constraint Date box, type or select 7/17/15.
7
Click OK .
Project applies a Start No Earlier Than constraint to the task, and a constraint icon
appears in the Indicators column. You can point to the icon to see the constraint
details in a ScreenTip.
To see a ScreenTip position the mouse pointer on a
constraint indicator (or any icon in the Indicators column).
9
Because this constraint affects the scheduling of the task, the Task Inspector pane
now includes the constraint details.