Adjusting working time for individual tasks
12
On the Task tab, in the Properties group, click Information .
The Task Information dialog box appears.
13
Click the Advanced tab.
As you can see in the Calendar box, the default for all tasks is None.
14
In the Calendar box, select Monday-Wednesday from the list of available base
calendars.
15
Click OK to close the dialog box.
Project applies the Monday-Wednesday calendar to task 29. The task calendar causes
Project to reschedule the task to the next available working day, which is the
following Monday. A calendar icon appears in the Indicators column, reminding you that
this task has a task calendar applied to it.
16
Point to the calendar icon.
A ScreenTip appears, showing the calendar details. Because of the custom calendar
you applied to this task, it will not be scheduled on a Thursday or Friday or over the
weekend.