In Depth Information
Setting up resource availability to apply at different times
You expect to have two copyeditors available to work on this project from the start of
the project through the month of April, three for the month of May, and then back to
two for the remainder of the project.
4
Under Resource Availability , in the first row of the Available From column, leave NA
(for Not Applicable).
5
In the Available To cell in the first row, type or select 4/30/15 .
6
In the Units cell in the first row, leave the 200% value.
7
In the Available From cell in the second row, type or select 5/1/15 .
8
In the Available To cell in the second row, type or select 5/31/15 .
9
In the Units cell in the second row, type or select 300% .
10
In the Available From cell in the third row, type or select 6/1/15 .
11
Leave the Available To cell in the third row blank. (Project will insert NA for you after
you complete the next step.)
12
In the Units cell in the third row, type or select 200% , and then press the Enter key.