Adjusting assignments in the Team Planner view
Next, you’ll assign the two unassigned and unscheduled tasks. Both of these tasks
should be assigned to Hany Morcos.
8 Click and drag the first unassigned task, Complete author questionnaire , to Hany
Morcos’s row so that the task start date is Monday, August 17.
9
Click and drag the remaining unassigned task, Schedule author interviews , to Hany
Morcos’s row so that the task start date is Tuesday, August 18.
Now both tasks are assigned and scheduled, though they remain manually
scheduled tasks.