Adjusting assignments in the Team Planner view
Project reassigns the task but does not change the task’s start or finish date or
duration.
TIP You can also reassign tasks by dragging them from one resource to another. To better
control the scheduling of tasks when you reassign them this way, set the timescale to daily
(to do this, on the View tab, in the Zoom group, click Days in the Timescale box).
There are still overallocation issues in the plan, but they are minor issues that don’t require
additional attention.
CLEAN UP Close the Advanced Assignments file.