Resolving resource overallocations manually
9
With Hany’s 8-hour assignment on the same task for Tuesday, August 25, selected,
type 4h and then press Tab.
10
Select Hany’s assignment of 8 hours on Friday, August 21, on the task Create mockup .
11
Type 4h , and then type 4h for each of Hany’s daily assignments on this task for
Monday and Tuesday.
12
If necessary, vertically scroll the view up until Hany’s name and the roll-up of her daily
assignments is visible.