Leveling overallocated resources
TIP If you are using Project Professional rather than Project Standard, the Resource
Leveling dialog box and some other dialog boxes contain additional options relating
to Project Server. (In this dialog box, the check box Level Resources With The
Proposed Booking Type is a Project Server–related option.) Throughout this topic,
we won’t use Project Server, so you can ignore these options for now. For more
information about Project Server, see Appendix C.
Now that you’ve reviewed the leveling options, you are ready to level the plan.
12
Click Level All .
TIP After you set the leveling options that you want in the Resource Leveling dialog
box, you can level the plan by clicking the Level All button on the Resource tab in the
Level group. You don’t need to return to the Resource Leveling dialog box unless you
want to change leveling options.
Project levels the overallocated resources.