Here, you can see many types of cost values for the overall plan (the total cost of the
project summary task 0), project phases (summary tasks), and individual tasks.
At this point in the project life cycle, the plan does not yet include a baseline;
therefore, the Baseline column contains only zero values. Similarly, the plan does not
yet contain any actual progress, so the Actual column contains only zero values.
Next, you’ll check the plan’s finish date.
3
On the Project tab, in the Properties group, click Project Information .
The Project Information dialog box appears.