Tracking actual and remaining values for tasks and assignments
To see more or less of the table on the left and the
timephased grid on the right, drag the divider bar left or right.
Double-clicking the divider bar will snap it to the nearest column.
7
In the Actual column for task 18, Original art review, type or click 92h , and then press
the Enter key.
Entering an actual value for the task causes Project
to distribute the actual values among the assigned
resources and adjust remaining work and other values.
Project highlights the most recently changed values.
Several important things occurred when you pressed Enter:
Project applied change highlighting to the updated values in the table.
The amount of actual work you entered was subtracted from the Remaining Work
column (labeled Remaining in the Project interface).
 