Tracking timephased actual work for tasks and assignments
This step concludes the actual work recorded at the task level. Next, you’ll enter
actual work values on a task at the assignment level.
For task 23, Copyedit , you have weekly actual work values from the assigned resource.
The copyeditors have completed the task. For this task, you’ll adjust the timescale to
record weekly actual values.
7
On the View tab, in the Zoom group, in the Timescale box, click Weeks .
8
Enter the following actual work values into the timephased grid for the Copyeditors’
assignment to task 23, Copyedit :
Date (Week of)
Actual Hours
May 31
60
June 7
80
June 14
48
The resource’s actual work values were rolled up to the task’s actual work values.
The original work values were saved in the baseline in case you need to refer to them
later.