Rescheduling incomplete work
1
On the View tab, in the Task Views group, click the down arrow below the Gantt
Chart button, and then click Gantt Chart .
2
Scroll the Gantt Chart view up so that the 1st Pages review (task 30) appears near the
top of the view.
3
In the Task Name column, click the name of task 31, Proofread and index .
Task 31, Proofread and index currently has two days of actual work completed and
several days of scheduled work remaining.
Progress bars indicate the portion
of the task that has been completed.
You have learned that over the weekend of August 1, a water pipe burst in the
proofreaders’ office. None of the project’s equipment or material was damaged, but
the cleanup will delay work until Wednesday, August 5. This effectively stops work on
the proofreading task for a few days. Next, you will reschedule incomplete work so
that the project can begin again on Wednesday.
4
On the Project tab, in the Status group, click Update Project .
The Update Project dialog box appears.
5
Select the Reschedule uncompleted work to start after option, and in the text box,
type or select 8/4/15 .