Saving a baseline saves a large set of task, resource, and assignment values in a plan.
Saving an interim plan, however, saves only the start and finish dates of tasks.
If you track work at the task level, work rolls down to the assignments. Conversely, if
you track work at the assignment level, work rolls up to the task level.
In usage views, you can change the time increments of the timescale to match the
time period against which you want to track. For example, if you want to record
actual work as full weeks, you can set the timescale to display weeks.
Should work on a project be interrupted for some reason, you can reschedule the
work to begin again on the date you specify.