This is the first task in the series of driving predecessor tasks for task 45. Earlier
tasks have been completed and no longer affect the scheduling of the remaining
incomplete tasks.
The new children’s book’s author, Tad Orman, and a copyeditor are assigned to the
task. After consulting with the assigned resources, you all agree that task 31 can be
completed in a slightly shorter duration: 12 days.
13
In the Duration field of task 31, type 12d , and then press the Enter key.
Project reduces the duration of the task and reschedules the affected successor tasks,
including task 45 and the project finish date.