8
Click the Task Name column heading.
This selects all tasks to be copied.
9
On the Task tab, in the Clipboard group, click the arrow next to Copy , and then click
Copy Picture .
The Copy Picture dialog box appears.
10
Under Render image , click To GIF image file , and then click Browse .
11
In the Browse dialog box, navigate to the Chapter19 folder, and then click OK .
12
Back in the Copy Picture dialog box, under Copy, click Selected Rows .
13
Under Timescale , in the From box, type or select 4/6/15 , and in the To box, type or
select 12/4/15 .
This date range matches the plan’s current start and finish date. You can see these
dates for task 0, the project summary task .