Views: Working with schedule details the way you want
4
On the View tab, in the Split View group, clear the Timeline check box.
Project hides the Timeline view. (The information in the view is not lost; it’s just
hidden for now.)
Next, you’ll switch to a sheet view.
5
On the View tab, in the Resource Views group, click Resource Sheet .
The Resource Sheet view replaces the Gantt Chart view.
The Resource Sheet view displays details about resources in a row-and-column
format (called a table ), with one resource per row. This view is called a sheet view .
Another sheet view, called the Task Sheet view , lists the task details. Also, notice that
the label of the contextual tab has changed to Resource Sheet Tools based on the
active view.
Note that the Resource Sheet view doesn’t tell you anything about the tasks to
which resources might be assigned. To see that type of information, you’ll switch to a
different view.
6
On the View tab, in the Resource Views group, click Resource Usage .