Updating a resource’s information in a resource pool
8
Click OK to close the Change Working Time dialog box.
Now William has no work scheduled on these two days (he did previously).
Because September 3 and 4 have been set
as nonworking days for this resource, no work
is scheduled on these days and they are
formatted as nonworking days for this resource.
To verify that William’s nonworking time setting was updated in the sharer plans, you
will look at his working time in one of those plans.
9
On the View tab, in the Window group, click Switch Windows , and then click
Consolidating A .