In Depth Information
Updating all plans’ working times in a resource pool
August 17 is set as a nonworking day in the resource pool.
21
6
Click OK to close the Change Working Time dialog box.
To verify that this change to the Standard base calendar in the resource pool was
updated in the sharer plans, you will look at working times in one of the sharer plans.
7
On the View tab, in the Window group, click Switch Windows , and then click
Consolidating A .
8
On the Project tab, in the Properties group, click Change Working Time .
The Change Working Time dialog box appears.
9
In the For calendar box, make sure that Standard (Project Calendar) is selected in
the drop-down list.
Note the Local book fair exception on August 17. All plans that are sharer plans of the
same resource pool will see this change in this base calendar.