Creating dependencies between plans
You need the book sales kit before you begin a task in the Consolidated B plan, so
you will create a task dependency between the two plans.
7
On the View tab, in the Window group, click Switch Windows , and then click
Consolidating B .
8
On the View tab, in the Task Views group, click Gantt Chart .
The Gantt Chart view appears.
9
Click the name of task 13, Interior illustration design .
10
On the Task tab, in the Editing group, click Scroll to Task .
Project scrolls the Gantt Chart view to display task 13.
11
On the Task tab, in the Properties group, click Information .
The Task Information dialog box appears.
12
Click the Predecessors tab and, directly below the existing predecessor value 12 in
the ID field, type Consolidating A\12 and then press Tab.