Finally, you can establish what puts a task on the critical path by specifying
the number of days of slack critical tasks might have. By default, tasks with
no slack are on the critical path. However, you can change this situation if
you want to be alerted that tasks with only one day of slack are critical —
figuring that one day isn’t much padding and that these tasks are still in
If you want all the settings on the Calculation tab to pertain to all projects,
click the Set as Default button before clicking OK to save the new settings in
the Options dialog box.